Saturday, October 22, 2016

Time & Work (Part - 6)

People Joining and Leaving the work

There are situations in which some people are added or removed, depending on requirement, to complete the work.

In these type of questions:
1. The individual time taken to complete the work is given.
2. Person joined / leaving the work is mentioned.
3. Asked to calculate the time / total time to finish the work.

How to tackle these problems at competitive level to attempt in least time. Here is the approach.

Before this, lets understand some basics:

Let A = 5/8 
Means A is capable of doing work for 8 days but, is doing only 5 days.
abd B = 3/7
Means B is capable of doing work for 7 days but, is doing only 3 days.
If we understand this concept, the things will be so easy.

Approach:
1. Work completed = 1 (Work must be completed)
2. Who is starting the work (A or B or Both)
3. Who is ending the work (A or B or Both)
If we try to find out these, our task becomes easy.
By forming a simple linear equation the problem is solved.

Example:

X and Y can do a work in 25 and 20 days respectively. Both together work for 5 days and then X leaves off. how many days will Y take to finish the rest work?

Sol:       Work completed = 1
             Who is starting  = Both X & Y
             Who is ending   = Y (Since X left the work)

                   X      +      Y     =   1

                  (5/25) + [(5+x)/20] = 1

Here x is extra days taken by Y to finish rest work (X left after 5 days).
Therefore,
                 1/5 + (5+x)/20  = 1
                  
                  4 + 5 + x = 20 (LCM = 20)
                                x = 20 - 9 = 11 days
NOTE: 1. Total work is completed in = 5+11=16 days
           2.  Remaining work is completed in = 11 days
---------------------------------------------------------------------------------

Example:

A and B can do a piece of work in 20 and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work lsat?

Sol:     Work completed = 1
             Who is starting  = A
             Who is ending   = A&B

here A already worked for 4 days and joined by B.
               
                      A      +      B     =   1
                  [(4+x)/20] + (x/12) = 1

                  3*(4+x) + 5*x = 1*60 (LCM = 60)

on solving we get, x = 6 days.
In the question, How long did the work lsat, means total days. Therefore the work is last for 4 + 6 = 10 days.
---------------------------------------------------------------------------------
Example:

A, B and C can complete a piece of work in 10, 12 and 15 days respectively. They started the work together, but A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?

Sol:     Work completed = 1
             Who is starting  = A, B and C
             Who is ending   = C

C worked from starting to ending (assume he took X days)

                     A     +     B     +      C       =   1
                 
            (X-5)/10 + (X-3)/12 + X/15 = 1

               6*(X-5) + 5*(X-3) + 4*X = 1*60

                6X - 30 + 5X - 15 + 4X = 60
               
                                    15X - 45 = 60
                  
                                           15X = 60+45=105

                                              X = 7 days               

---------------------------------------------------------------------------------
Practice Questions
---------------------------------------------------------------------------------
1. A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
                  A. 3 days
                  B. 5 days
                  C. 10 days
                  D. 12 days
---------------------------------------------------------------------------------
2. A and B together can do a piece of work in 12 days which B and C together do in 16 days. If A works for 5 days, B works for 7 days than C complete the remaining work in 13 days. In how much time B alone do the whole work?
                  A. 12 days
                  B. 24 days
                  C. 16 days
                  D. 48 days
---------------------------------------------------------------------------------
Practice more number of questions from any standard book to master the concept. Leave a comment in comment box. Share with others to help them.
---------------------------------------------------------------------------------

No comments:

Post a Comment